Construction Impacts Meeting Generates Many Questions, Few Answers

2 days ago
4 min read

[November 23, 2026]


Portland Public Schools (PPS) held a community information session at Wells High School on November 18. Representatives from PPS and Hoffman Construction walked attendees through the construction logistics plan.


Where is PBOT?

As the session progressed, it became clear that project staff were unable to answer many of attendees' questions about parking and traffic impacts, referring them to the Portland Bureau of Transportation (PBOT), who unfortunately did not have a representative at the meeting.

The sidewalk on the east side of the northern end of the parking lot between Rieke and Wells is temporarily closed.
The sidewalk on the east side of the northern end of the parking lot between Rieke and Wells is temporarily closed.

Several times, project staff responded that particular issues fall under the purview of the PBOT, while acknowledging that finding the right person at the bureau can be difficult. While the responses were not unsympathetic, the best advice they could offer is to consult the PBOT website for contact information.


This left many attendees frustrated. In response, the Hillsdale Neighborhood Association (HNA) has begun planning another community meeting focused on construction impacts, this time with both PBOT and Wells construction staff. The goal is to hold the meeting in January or February.


Unanswered questions include:

  • “Rieke Road” will soon be permanently closed to vehicular through-traffic. How will the resulting impacts throughout the neighborhood of this closure be mitigated? For example, could traffic signal timing at Bertha Ct. and Vermont St. be adjusted to accommodate increased traffic? How will new traffic patterns be managed on other neighborhood streets and at the north entrance to campus from Capitol Hwy?

  • The sidewalk on the north side of Vermont will be closed for two to three years. Could a permanent sidewalk be installed on the south side of the street?

  • Where can residents go with concerns about neighborhood parking and traffic impacts? A single point-of-contact would be helpful.


And a bonus question for TriMet: There will be a drastic decrease in the number of student parking spaces during construction. Will TriMet add busses to account for the potential increase in students taking the bus?


Construction Logistics

Construction and staging have begun. The first phase, construction of the new high school building, is expected to be completed by fall 2029. Phase 2 will begin in 2029 and last approximately one year. It will include demolition of the old school building and construction of new athletic fields.


Construction hours will be 7am-6pm.


During the excavation phase, hundreds of trucks trips per week will be needed  to haul approximately 107,000 bank cubic yards of soil off-site. An automated truck wash, rumble strips, and street sweepers will be used to keep the dirt in the trucks or on the site, and not on neighborhood streets.


Construction logistics plan showing sidewalk closures, temporary paths, site circulation, fences, and other items relating to Phase 1 of construction. Click image to enlarge.
Construction logistics plan showing sidewalk closures, temporary paths, site circulation, fences, and other items relating to Phase 1 of construction. Click image to enlarge.

Pickleball Courts and Pool

The pickleball courts will remain open during Phase 1 of construction.


The public pool, owned and operated by Portland Parks & Recreation, will remain open during the summer in Phase 1. Hoffman project superintendent Jacob McKay said a decision about whether the pool can operate during Phase 2 will be made later.


Vehicle, Pedestrian and Bicycle Circulation

Some significant changes to local circulation during construction include:


  • The north end of the parking lot between Rieke and Wells will be closed.

  • Pedestrian and bicycle access along the “Rieke Road” will remain open, as will the east-west path on the north side of the campus.

  • Much of the sidewalk on Vermont between Rieke and Wells will be closed, Temporary crosswalks and pedestrian paths will be provided, including a temporary path along the south side of the street.

  • The road that circles the north and east sides of campus from the Capitol Highway entrance will be closed to through-traffic. The Wells vehicle entrance from Vermont will remain open, with a turnaround near the grandstand on the north side.

  • TriMet will continue serving stops on the north side of Vermont Street, although some stops will be relocated.

  • There will be no north-south pedestrian through-access on the west side of the existing building. The area between the construction area and the existing building will be gated, with access restricted except in emergencies. McKay said he is willing to discuss opening the pathway during the summer to provide easier pool access from the south side.


The planned temporary path on the south side of Vermont generated considerable discussion. Many attendees questioned the plan to use 1/4-inch gravel and asked whether a better surface could be provided. Others raised the possibility of installing permanent concrete sidewalks. McKay agreed to explore alternatives for the temporary path but said permanent sidewalks would be a matter for PBOT to address.


Parking, Traffic

Construction staff parking: Limited worker parking will be available inside the construction fence, but not enough to accommodate all workers. Hoffman will encourage carpooling and provide incentives. Efforts to secure offsite parking at nearby surface lots were not successful and would have added significantly to the costs. The parking spaces on Vermont directly in front of the existing building will remain open for parking. Construction workers will be discouraged from using them. Neighboring residents and businesses are encouraged to report illegal parking by construction workers.


School staff parking: School staff will continue to park in the existing parking lots.


Student parking: Student parking will be significantly reduced during construction. Students will be encouraged to bike or bus to school. Parents asked if the number of bike parking spots would be increased during construction or if TriMet plans to increase service. One parent commented that it’s already challenging for students to arrive on time because busses are full. Others expressed doubts that more students would choose to arrive at school by bike. Project staff said they would explore adding more bike parking during construction and would ask TriMet if it plans to increase service.


Wells student drop-off: A drop-off area will be available just off Capitol Highway, although parents are encouraged instead to drop off students on Vermont Street at the front entrance to the school. The Capitol Highway location is expected to become congested.


Next steps

Project staff were receptive to attendees' ideas and suggestions and agreed to explore alternative solutions to several concerns. They also committed to holding additional community meetings, possibly beginning six months into construction.


Watch for updates on HNA's efforts to arrange a separate meeting with PBOT officials.


Contact information for Hoffman Construction:

Contact information for Portland Public Schools Wells project staff:

—Valeurie Friedman